Note: As the Council continues to manage the risk of Covid-19 public attendance at this meeting will be limited and anyone wishing to attend is asked to contact democratic.services@trafford.gov.uk to register in advance . The Council has a duty to protect the health, safety and welfare of staff and others from Covid transmission risks so far as is reasonably practicable and all attendees are reminded of the need for self-isolation where positive cases and contacts have been identified. Please note that the meeting will also be streamed live in line with the principles of openness and transparency in local government. To access the live stream of the meeting, please paste the following into your browser's address bar: https://www.youtube.com/channel/UCjwbIOW5x0NSe38sgFU8bKg 

Items
No. Item

56.

Rixton and Warburton Toll Bridge - Transport and Works Act Order pdf icon PDF 303 KB

To consider a report of the Executive Member for Housing and Regeneration.

Additional documents:

Minutes:

 

The Executive Member for Housing and Regeneration submitted a report advising the Council that the Manchester Ship Canal Company had submitted an application for an Order under Section 3 of the Transport and Works Act 1992, proposing new procedures for the operation of the Rixton and Warburton Toll Bridge, including new tolls, concessions, byelaws and collection arrangements.

 

The report detailed a Trafford Council response to the Order which raised a number of objections to the proposed changes, particularly around the increased toll charge and lack of provision for local resident discounts. The response had to be submitted by 18 January 2022.

 

The Executive Member for Housing and Regeneration had also submitted a supplementary report proposing that objection be raised to an additional issue, the proposed transfer of the Bridge into a new company separate to the Manchester Ship Canal Company.

 

Speaking to the reports, Councillor Wright, the Executive Member for Housing and Regeneration clarified that the level of the toll proposed was in fact £1.00 inclusive of VAT per crossing.

 

It was moved and seconded that the Executive’s recommendations set out in both the report and supplementary report be approved.

 

Following a debate on the matter, the Motion was agreed with the unanimous consent of the Council.

 

RESOLVED:

 

(1)       That the Council submits an objection to the Rixton and Warburton Toll Bridge Transport and Works Act Order as set out in Appendix 1 to the report.

 

(2)       That, in addition to the objections referenced in the original report, the Council submits an objection to the Rixton and Warburton Toll Bridge Transport and Works Act Order, as set out in paragraph 2.2 of the supplementary report.

 

(3)       That the Corporate Director of Place be delegated authority to prepare detailed submissions and take any other necessary steps to pursue and progress the objection to the order, including negotiations with the Manchester Ship Canal Company and that any further concessions shall be agreed, in consultation with the Executive Member for Housing and Regeneration.