To receive and, if so determined, to approve as a correct record the Minutes of the meeting held on 11th July, 2013.
Minutes: RESOLVED: That the Minutes of the meeting held on 11th July, 2013, be approved as a correct record and signed by the Chairman. |
|||||||||||||||||||||||||||||
ADDITIONAL INFORMATION REPORT To consider a report of the Acting Chief Planning Officer, to be tabled at the meeting. Minutes: The Acting Chief Planning Officer submitted a report informing Members of additional information received regarding applications for planning permission to be determined by the Committee.
RESOLVED: That the report be received and noted.
|
|||||||||||||||||||||||||||||
APPLICATIONS FOR PERMISSION TO DEVELOP ETC. PDF 61 KB To consider the attached reports of the Acting Chief Planning Officer. Additional documents: Minutes:
|
|||||||||||||||||||||||||||||
APPLICATION FOR PLANNING PERMISSION 80433/FULL/2013 - NEW CARE PROJECTS LLP - LAND ADJACENT TO ALLINGHAM HOUSE CARE CENTRE, DEANSGATE LANE, TIMPERLEY Minutes: The Acting Chief Planning Officer submitted a report concerning an application for planning permission for the erection of a detached three storey building to provide self-contained accommodation associated with the adjacent Allingham House Elderly Care Home.
RESOLVED –
(A) That the application will propose a satisfactory development for the site upon the completion of an appropriate Legal Agreement and that such Legal Agreement be entered into to secure a maximum financial contribution of £9,346 split between £1,616 towards Highway and Active Travel infrastructure, £5,560 towards Public Transport Schemes and £2,170 towards Specific Green Infrastructure (to be reduced by £310 per tree planted on site in accordance with an approved landscaping scheme).
(B) In the circumstances where the S106 Agreement has not been completed within 3 months of the resolution to grant planning permission or the 8 week target date whichever timescale comes first, the final determination of the application shall be delegated to the Acting Chief Planning Officer.
(C) That upon the completion of the above Legal Agreement, planning permission be granted subject to the conditions now determined.
|
|||||||||||||||||||||||||||||
APPLICATION FOR PLANNING PERMISSION 80836/FULL/2013 - MR. THOMAS THORNS - 41 MANCHESTER ROAD, ALTRINCHAM Minutes: The ActingChief Planning Officer submitted a report concerning an application for planning permission for the demolition of existing detached garage and erection of two semi-detached dwellings, detached garage to rear and alterations to existing vehicular access.
RESOLVED –
(A) That the application will propose a satisfactory development for the site upon the completion of an appropriate Legal Agreement and that such Legal Agreement be entered into to secure a maximum financial contribution of £5,730.37 split between £3,885.63 towards Specific Green Infrastructure (to be reduced by £310 per tree planted on site in accordance with an approved landscaping scheme) and £1,844.74 towards Spatial Green Infrastructure, Sports and Recreation and to include an overage clause to ensure that an appropriate commuted sum up to a maximum of £32,584.26 is provided should the developer’s level of net profit be better than predicted in the viability appraisal.
(B) In the circumstances where the S106 Agreement has not been completed within 3 months of the resolution to grant planning permission or the 8 week target date whichever timescale comes first, the final determination of the application shall be delegated to the Acting Chief Planning Officer.