1. That approval be given to the:-
Ø Capital Programme as detailed in Appendix 2 of the report;
Ø Schemes to be undertaken from the “block” budget allocations reported in paragraph 21 and detailed Appendix 4 to the report.
2. That it be recommended that the Council approve:-
Ø the Capital Strategy as included at Appendix 1 to the report;
Ø the overall Capital Programme in the sum of £368.72m for the period 2020/23, comprising £168.72m in respect of the General Capital Programme and £200m for the Investment Fund, inclusive of the proposed £100m addition,
Ø additional prudential borrowing of £6.92m to support revenue generating investment opportunities as detailed in Paragraph 11 of the report; and £100m to support the Asset Investment Strategy; and
Ø the Prudential and Local Indicators as set out at Appendix 3 to the report.